Concrete Floors

houselogo.jpgLast Saturday, we finished putting on the mud sills, and installed one of the beams (the one under the front bedroom). On Monday, the concrete crew installed the drainage tile, poured and trowled the concrete floor of the basement and of the garage, and backfilled around most of the foundation. They cut the garage floor and installed the basement window wells on Tuesday. My father framed up the landing for the stairway and the support wall in the basement on Wednesday. Yesterday and today, he got that wall up and put in the other beams. Tomorrow, me and a bunch of relatives are putting in the floor joists.

Below are pictures of the progress up through Monday.